Thursday, October 6, 2011

Evacuated 2011 - Day 107 - Oct 6, 2011

The house could almost be considered a blank slate as far as the infrastructure goes. Yesterday we pulled out the 2 water heaters, the 2 furnaces, all the gas lines and all the plumbing lines. The heating and A/C is now scheduled for the 27th of this month. A plumber is coming from Idaho. He will take the ND test to get licensed on the 18th and should start our house on the 19th. I am going to order kitchen cabinets today.... they should be here about the 1st week of November. Waiting for the floors to dry out a bit more on main floor so the sub flooring can go down..... the are a bit damp due to concrete curing in basement and the power washing that was done last weekend. The contractors are going to start today .... removing the balance of the lathe and plaster on main floor and rebuilding the missing walls in the basement. Then we will get the electricians back to finish the main floor and wire the basement...... things are progressing.